How to Set Up a Metering Pump From Scratch Without the Drama
A metering pump is the heart of your chemical feed system. When set up improperly, it becomes a source of leaks, air locks, and inconsistent dosing, which translates directly to wasted chemical, regulatory risk, and costly downtime.
At Vissers Sales Corp, we believe precision starts on day one. We’ve distilled decades of field experience into a simple checklist to ensure your installation is accurate, safe, and repeatable – without the drama.
What You Need – Preparation is Everything
Before you unbox, gather these essential components. Do not cut corners, especially on safety and verification.
- Pump, manual, and mounting hardware.
- Suction and discharge tubing, a foot valve/strainer.
- Safety and Control: A relief valve, a back-pressure valve, and an injection quill with a check tip.
- Verification: A calibration column with isolation valves.
- Safety: The correct Personal Protective Equipment (PPE) and a chemical-matched spill kit.
1. Mounting for a Flooded Suction (The Foundation)
The goal is to let gravity work for you, not against you.
- Location is Key: Set the pump on a rigid, level base at or, ideally, below the day tank outlet (this is called flooded suction and is the best practice).
- Keep it Tight: Keep the pump as close as possible to the chemical source to minimize the suction line length.
- Mistake to Avoid: Placing the pump above the tank. This forces the pump to fight suction lift, which is a common cause of air locks and flow issues.
2. Building a Short, Clean Suction Run
The suction line is the most sensitive part of the system. Turbulence here invites air and cavitation.
- Path of Least Resistance: Use the shortest, straightest line possible, with an Internal Diameter (ID) equal to or larger than the pump’s port.
- Test-Ready: Install the calibration column between the tank and the pump. This is critical for proving your dose later.
- Gassy Chemicals: For chemicals like hypochlorite, install a degassing head or a short vertical rise to allow trapped gas bubbles to escape before they reach the pump head.
3. Safe Discharge – Pressure, Protection, and Mixing
The discharge side is where you control pressure and ensure safe chemical delivery.
- Essential Safety: Install a relief valve near the pump discharge. Pipe its outlet safely back to the tank or a closed return vessel. This prevents over-pressurization.
- Steady Flow: A pulsation dampener (highly recommended) calms line chatter, while a back-pressure valve is installed downstream to ensure the pump’s check valves seal correctly.
- Proper Injection: The injection quill is non-negotiable. It ensures the chemical reaches the host pipe’s centerline and mixes properly. Tying directly into the pipe wall causes poor mixing and corrosion.
4. Priming Without the Mess
Always wear your PPE. Priming removes air, and air is the enemy of accuracy.
- The Process: Open the suction valve from the tank. Run the pump at a low speed, cracking the bleed/prime valve (if fitted) to release air. Close the bleed valve as soon as you see a solid stream of liquid.
- Mistake to Avoid: Never run a pump dry for long. Even a brief dry run can damage the head on certain pump designs.
5. Setting Initial Controls and Back Pressure
You are establishing your operating envelope here.
- Pump Controls: Set the stroke length to the mid-range and adjust the speed to meet your estimated flow rate. This leaves room for fine adjustments later.
- Valve Setpoints:
-
- Back-Pressure Valve: Set this to your starting value.
- Relief Valve: Verify its setpoint is approximately 10-15% above your normal running pressure, but safely below the pressure limit of the weakest system component.
6. Run Your First Calibration Check
A flow meter tells you that something is flowing. A calibration column tells you exactly how much. This is the only true way to verify your actual dose.
- Stabilize the pump at your target settings.
- Close the tank suction valve and open the column suction valve. The pump now draws from the column.
- Time the drawdown between two clear marks with a stopwatch.
- Calculate actual flow.
- Adjust speed (for fine trim) or stroke (for coarse change) and repeat until you are within ±5% of your target.
- Don’t Forget: Reopen the tank suction and close the column valve.
If you want help selecting calibration columns, quills, and the right back-pressure and dampening setup for your line, our team can review your system and provide a simple, high-confidence configuration. Call Vissers Sales Corp at 1-800-367-4180 or visit our industrial pump accessories page to get started.